The Green Light Plan > Projects > Projects Under Construction
GREEN LIGHT PLAN
Projects Under Construction
| Project ID | Project Name | Start Date | Duration | Contractor | Look Ahead |
| 97C200a | Central Thruway Phase I Bridges Comite River and Beaver Bayou No. 1 Bridges |
04/10/2008 | 30 Months | L&A Contracting Company | |
| H | Lobdell Improvements | 10/06/2008 | 9 Months | Barber Brothers Contracting Co., LLC | |
| CC | Highland Road | 01/12/2009 | 23 Months | Denton-James, LLC | |
| F | Staring Lane Extension | 02/02/2009 | 21 Months | James Construction Group, LLC | ![]() |
| E | Jones Creek Road (Segment 3) |
02/23/2009 | 18 Months | Barber Brothers Contracting Co., LLC | |
| 97C | Central Thruway Phase I Bridges Sullivan and CN&IC Railroad Bridges |
03/11/2009 | 22 Months | James Construction Group, LLC | |
| X | Siegen Lane | 06/15/2009 | 24 Months | Byron E. Talbot Contractor, Inc. | |
| R1 | Pecue Re-alignment at Perkins Road | 07/27/2009 | 6 Months | Boone Services, Inc. | |
| K | Brightside Lane | 09/08/2009 | 9 Months | F. G. Sullivan, Jr. Contractor, LLC | |
B C 02N |
Southeast Area Group Project O'Neal Lane (Segment 1) South Harrell's Ferry Road (Segment 2) O'Neal Lane Embankment |
09/28/2009 | 24 Months | Barber Brothers Contracting Co., LLC | |
| 02Q | South Harrell's Ferry Road (Segment 1) | 11/09/2009 | 21 Months | James Construction Group, LLC | |
| 02L | Comite Drive | 11/15/2009 | 11 Months | J. B. James Construction, LLC | |
| U | Perkins at Stanford/Acadian | 11/21/2009 | 3 Months | RCS Contractors, Inc. | |
| 02P | S. Choctaw at N. Flannery Intersection | 01/05/2010 | 6 Months | Hard Rock Construction, LLC |