Project ID: 02N  Project Layout
Project Name: ONeal Lane
City Parish Project No: 02-CS-HC-0004
DOTD Project No:
Design Engineer: DPW
Project Limits: S Harrell's Ferry Road, south to George O'Neal
Project Linear Footage: 6767
Detailed Description: This project will add two additional through lanes and sidewalks from South Harrell’s Ferry Road to George O’Neal. It will extend the adjacent improved section of O’Neal Lane (from South Harrell’s Ferry Road to 1,250’ south of Interstate 12) and when combined with other projects in the Green Light Plan will provide an improved north-south connection extending from Nicholson Drive to Hooper Road.
Project Budget: Present Day Cost $17,911,451.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 90% ROW 100% Construction 0%
                                           
Project Progress: 100% paper plans were received in July. Bridge plans are still in design.
Project Look Ahead: DPW will be producing bridge plans with submittal expected in September 2010.

CONSTRUCTION INFORMATION
Contractor Name: Barber Brothers Contracting Company, LLC
Construction Amount: $476,549.50
Construction Duration:
Construction Start Date:
Construction End Date: