S Harrells Ferry Road Seg 1

PROJECT INFORMATION
Project ID: 02Q  Project Layout
Project Name: S Harrells Ferry Road Seg 1
City Parish Project No: 02-CS-HC-0007
DOTD Project No:
Design Engineer: ABMB Engineers, Inc.
Project Limits: South Sherwood Forest Boulevard to Millerville Road
Project Linear Footage: 9570
Detailed Description: This project will add two additional through lanes, sidewalks, and a raised median to South Harrell's Ferry Road from south Sherwood Forest Boulevard to Millerville Road. The project will require two bridges (one east bound lane bridge and one west bound lane bridge) crossing Jones Creek. This project will extend the improvements on South Harrell's Ferry Road (east of Millerville Road) and the expanded Millerville roadway (from Old Hammond Hwy. to S. Harrell's Ferry Road). When combined with other projects in the Plan, it will provide an improved east-west connection in this area.
Project Budget: Present Day Cost $25,296,884.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 15%
                         
Project Progress: Contractor continuing with drainage and sanitary sewer installation. Utility companies are completing relocations.
Project Look Ahead: Bridge pile driving, embankment and subsurface drainage construction.

CONSTRUCTION INFORMATION
Contractor Name: James Construction Group, LLC
Construction Amount: $ 13,194,885.90
Construction Duration: 630 Days
Construction Start Date: 11/9/2009
Construction End Date: 8/17/2011

Secure Login For questions and comments about this Green Light Plan project, please send email requests to Kimberlie Wessman at wessman@csrsonline.com or use our online feedback form.

This page was last updated on 9/1/2010 5:29:44 PM