Jones Creek Road Seg 3

PROJECT INFORMATION
Project ID: E  Project Layout
Project Name: Jones Creek Road Seg 3
City Parish Project No: 06-CS-HC-0051
DOTD Project No: TBD
Design Engineer: SIGMA Consulting Group, Inc.
Project Limits: Coursey Boulevard to South Harrell's Ferry Road
Project Linear Footage: 6810
Detailed Description: This project will widen Jones Creek Road to provide two through lanes in each direction, sidewalks and raised median. It will also require a new bridge crossing and realignment at Jones Creek. When combined with other projects in the Plan, it will provide an improved north-south connection extending from Nicholson Drive to Hooper Road.
Project Budget: Present Day Cost $21,081,824.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 70%
                         
Project Progress: Traffic has been shifted to the northbound lanes and the southbound bridge is being completed. Drainage is being installed for the southbound lanes between the bridge and S. Harrell's Ferry Road.
Project Look Ahead: Construction of the northbound bridge and the southbound lanes between the bridge and S. Harrell's Ferry Road.

CONSTRUCTION INFORMATION
Contractor Name: Barber Brothers Contracting Company, L.L.C.
Construction Amount: $12,357,317.25
Construction Duration: 678
Construction Start Date: 2/23/2009
Construction End Date: 1/2/2011