Fairchild - Badley Road

PROJECT INFORMATION
Project ID: FF  Project Layout
Project Name: Fairchild - Badley Road
City Parish Project No: 06-CS-HC-0018
DOTD Project No: N/A
Design Engineer: Pan American Engineers
Project Limits: Scenic Highway to Veterans Boulevard and 600' of Elm Grove Garden
Project Linear Footage: 6020
Detailed Description: This project will replace Fairchild-Badley Road - a narrow, two lane open ditch roadway - with a two lane curb and gutter street. Sidewalks will also be included in the project. Six hundred feet of the Elm Grove Garden project (from the Fairchild-Badley Street intersection to the bridge 600' to the north) will be added to this project to facilitate construction.
Project Budget: Present Day Cost $5,706,620.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 20% Construction 0%
                                           
Project Progress: Final plans for Fairchild-Badley are complete. The GLP right of way team is starting appraisals and acquisitions.
Project Look Ahead: Right of way appraisers and agents are continuing the appraisal and acquisition process.