Coursey Blvd at Sherwood Forest Blvd

PROJECT INFORMATION
Project ID: GG  Project Layout
Project Name: Coursey Blvd at Sherwood Forest Blvd
City Parish Project No: 06-CS-TL-0035
DOTD Project No: TBD
Design Engineer: Justice and Huang Engineers, Inc.
Project Limits: Intersection Improvements
Project Linear Footage: 0
Detailed Description: The Coursey Boulevard and Sherwood Forest Boulevard intersection improvement project adds several turn lanes, which requires some right of way acquisition.
Project Budget: Present Day Cost $7,522,525.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 100%
       
Project Progress: This project has been completed.
Project Look Ahead: Construction was completed for this project on March 25, 2009. The project was completed 84 days ahead of schedule.

CONSTRUCTION INFORMATION
Contractor Name: Hard Rock Construction
Construction Amount: 6,277,954.35
Construction Duration: 150 days
Construction Start Date: 1/12/2009
Construction End Date: 3/25/2009

Secure Login For questions and comments about this Green Light Plan project, please send email requests to Kimberlie Wessman at wessman@csrsonline.com or use our online feedback form.