US 61 - LA Hwy 64 (Mt. Pleasant)

PROJECT INFORMATION
Project ID: HH1  Project Layout
Project Name: US 61 - LA Hwy 64 (Mt. Pleasant)
City Parish Project No: 07-TL-HC-0025
DOTD Project No: 253-02-0026 & 019-02-0052
Design Engineer: Evans-Graves Engineers, Inc.
Project Limits: Intersection
Project Linear Footage: 0
Detailed Description: The proposed project consists of adding additional lanes to provide a right turn lane for northbound US 61, improve the westbound approach of LA 64 to a four-lane divided roadway with raised median and open ditches, and upgrade the signalization for the intersection.
Project Budget: Present Day Cost $1,633,570.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 0%
                         
Project Progress: The consultant has submitted final plans and mylars.
Project Look Ahead: The GLP PM is preparing Bid Documents. The right of way has been acquired and utility relocations have begun.