PROJECT PROGRESS



Ford Street

PROJECT INFORMATION
Project ID: I  Project Layout
Project Name: Ford Street
City Parish Project No: 04-CS-CI-0019
DOTD Project No: TBD
Design Engineer: ABMB Engineers, Inc.
Project Limits: Plank Road to Mickens Road
Project Linear Footage: 7340
Detailed Description: This project will replace the current narrow, two lane, open ditch roadway on Ford Street with two 12’ travel lanes, sidewalks and a raised median. This will provide a significantly improved East-West connection between Plank Road and Mickens Road.
Project Budget: Present Day Cost $15,209,286.00
2007 Estimates
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 99% Construction 12%
                                           
Project Progress: Utility companies continue with relocations. Drainage installation and construction of base course continuing on the north side at the east end of the project. Grading work has started on the west end of the project.
Project Look Ahead: Continue with the installation of base course on the east end of the project and grading work on the west end.

CONSTRUCTION INFORMATION
Contractor Name: Richard Price Contracting Co., LLC
Construction Amount: $6,042,106.55
Construction Duration: 360 Calendar Days
Construction Start Date: 5/3/2010
Construction End Date: 4/28/2011