Veterans Memorial Blvd. Extension

PROJECT INFORMATION
Project ID: JJ  Project Layout
Project Name: Veterans Memorial Blvd. Extension
City Parish Project No: 06-CS-HC-0010
DOTD Project No: N/A
Design Engineer: Forte & Tablada, Inc.
Project Limits: Harriet Quimby to Blount Road
Project Linear Footage: 4120
Detailed Description: This project will consist of extending the existing four lane boulevard curb and gutter roadway from it's terminus at Harriet Quimby north, to the new terminus point at Blount Road. A right turn and left turn lane will be constructed from Blount Road on to Veterans Memorial Boulevard.
Project Budget: Present Day Cost $5,369,378.00
2007 estimates with Construction Contract Amount
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 100%
       
Project Progress: Construction complete. Roadway opened to traffic on October 2, 2008.
Project Look Ahead:

CONSTRUCTION INFORMATION
Contractor Name: Denton-James, LLC
Construction Amount: $4.535 Million
Construction Duration: 305 Calendar Days
Construction Start Date: 10/29/2007
Construction End Date: 10/1/2008