PROJECT PROGRESS



Brightside Lane

PROJECT INFORMATION
Project ID: K  Project Layout
Project Name: Brightside Lane
City Parish Project No: 06-CS-HC-0027
DOTD Project No: 817-16-0029
Design Engineer: URS Corporation
Project Limits: River Road to Nicholson Drive
Project Linear Footage: 11350
Detailed Description: The project will provide a three lane section for Brightside Lane from River Road to west of Nicholson Drive. The project will include sidewalks and dedicated bike lanes on both sides of the road. It will tie into the Nicholson @ Brightside / W. Lee Intersection Improvements project. The proposed roadway will be constructed within the existing right of way.
Project Budget: Present Day Cost $12,967,990.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 70%
                         
Project Progress: The contractor is continuing the road widening. Sewer construction between River Road and River Bend will continue throughout September. All utility relocations are completed.
Project Look Ahead: Drainage installation is following the sewer installation. Construction of new sidewalks has begun on the east end of the project and is progressing to the west. Roadway widening on the south side will immediately follow the completion of the sewer and drainage installation.

CONSTRUCTION INFORMATION
Contractor Name: F. G. Sullivan, Jr. Contractor, LLC
Construction Amount: $7,122,216.80
Construction Duration: 270 Days
Construction Start Date: 9/8/2009
Construction End Date: 6/5/2010

Secure Login For questions and comments about this Green Light Plan project, please send email requests to Kimberlie Wessman at wessman@csrsonline.com or use our online feedback form.

This page was last updated on 9/1/2010 5:29:44 PM