Nicholson Drive Seg 1

PROJECT INFORMATION
Project ID: L  Project Layout
Project Name: Nicholson Drive Seg 1
City Parish Project No: 08-CS-HC-0035
DOTD Project No: 414-01-0039
Design Engineer: Forte & Tablada, Inc.
Project Limits: 500’ North of Brightside Lane / West Lee Drive to 400’ South of Gourrier Avenue
Project Linear Footage: 6040
Detailed Description: Nicholson Drive, Segment 1 is currently a two lane roadway with shoulders from Brightside Lane to Gourrier Avenue. There is a railroad and a bike lane on the west side of the roadway. The proposed typical section is a four-lane curb and gutter roadway with a raised median and a widened sidewalk on the east side of the roadway. The project will provide significantly improved access into and out of the LSU area and Downtown Baton Rouge along with an improved connection to the proposed Nicholson @ Brightside / West Lee Intersection Improvement (GLP Project L1) and Brightside Lane improvement (GLP Project K).
Project Budget: Present Day Cost $26,035,803.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 90% Design 0% ROW 0% Construction 0%
                                                                               
Project Progress: The design consultant resubmitted the design study that addresses the preliminary Design Study review comments.
Project Look Ahead: The Design Study will be reviewed and finalized.