PROJECT INFORMATION
Project ID: L1  Project Layout
Project Name: Nicholson Dr at Brightside Ln / West Lee
City Parish Project No: 01-CS-US-0017
DOTD Project No: 700-17-0177
Design Engineer: Forte & Tablada, Inc.
Project Limits: Intersection
Project Linear Footage: 0
Detailed Description: Proposed project will improve the intersection to include two through lanes, and a left turn lane for all four approaches.
Project Budget: Present Day Cost $9,430,232.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 60% ROW 0% Construction 0%
                                                             
Project Progress: The review of the 60% Final Plans is complete. The design consultant will start preparing the next submittal.
Project Look Ahead: The required right of way taking lines for the project will be finalized in September.

Secure Login For questions and comments about this Green Light Plan project, please send email requests to Kimberlie Wessman at wessman@csrsonline.com or use our online feedback form.

This page was last updated on 9/1/2010 5:29:44 PM