PROJECT PROGRESS



N Harrells Ferry Road

PROJECT INFORMATION
Project ID: M  Project Layout
Project Name: N Harrells Ferry Road
City Parish Project No: 04-CS-CI-0041
DOTD Project No: N/A
Design Engineer: SIGMA Consulting Group, Inc.
Project Limits: 250' south of Old Hammond Hwy (LA 426) to 500' west of Sherwood Forest Blvd.
Project Linear Footage: 1775
Detailed Description: This project will replace a narrow two-lane open ditch roadway with a two-lane curb & gutter roadway that will include a continuous center turn lane from 250 feet south of the Old Hammond Hwy. (LA 426) intersection, recently constructed by LA D.O.T.D., to 500 feet west of Sherwood Forest Blvd.
Project Budget: Present Day Cost $2,756,729.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 100%
       
Project Progress: Ribbon cutting ceremony was held on Thursday, March 5, 2009. The roadway is open to traffic.
Project Look Ahead: Project final acceptance by the East Baton Rouge Metropolitan Council.

CONSTRUCTION INFORMATION
Contractor Name: Industrial Enterprises, Inc.
Construction Amount: 1,811,104.67
Construction Duration: 365 days
Construction Start Date: 5/5/2008
Construction End Date: 3/5/2009

Secure Login For questions and comments about this Green Light Plan project, please send email requests to Kimberlie Wessman at wessman@csrsonline.com or use our online feedback form.