Perkins Road Seg 1

PROJECT INFORMATION
Project ID: Q  Project Layout
Project Name: Perkins Road Seg 1
City Parish Project No: TBD
DOTD Project No: TBD
Design Engineer: TBD
Project Limits: 400' east of Siegen Lane to 200' east of Pecue Lane
Project Linear Footage: 7560
Detailed Description: Perkins Road is currently a two-lane roadway without shoulders from Siegen Lane to Pecue Lane. The proposed typical section is a four lane curb and gutter roadway with a raised median and sidewalks on both sides. This project will be an extension of the City-Parish / LA DOTD Perkins Road project that is currently under construction from Essen Lane to Siegen Lane and will tie directly to the proposed project at Siegen Lane and Pecue Lane. When combined with other projects currently under construction or contained in this plan, a continuous four to five lane section will extend from I-10 / Highland Road, to I-10 near the downtown area.
Project Budget: Present Day Cost $26,947,500.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 30% Design 0% ROW 0% Construction 0%
                                                                               
Project Progress: DOTD has initiated a Stage 0 Phase on this segment of Perkins Road. The Stage 0 Phase was completed in November 2009.
Project Look Ahead: GLP will proceed based on funding.