| Project Limits: |
3000' west of Bluebonnet Boulevard to 750' south of Highland Road |
| Project Linear Footage: |
12330 |
| Detailed Description: |
This project will consist of adding two additional traffic lanes, turn lanes and improvement to the intersections from a point 3000' west of the Bluebonnet Boulevard to the tie-in point approximately 750' south of Highland Road. The purpose of the project will be to provide an improved east-west route to LSU and the Downtown areas, and relieve the congestion along Highland Road. Identified on the City-Parish Major Street Plan, the improved Burbank Drive will tie to north-south improvements along Bluebonnet Boulevard and Siegen Lane. |
| Project Budget: |
Present Day Cost $6,452,730.00
2007 estimates with Construction Contract Amount
|
| Project Files: |
|
|