Staring Lane Extension 1

PROJECT INFORMATION
Project ID: F  Project Layout
Project Name: Staring Lane Extension 1
City Parish Project No: 06-CS-HC-0030
DOTD Project No: 257-04-0026
Design Engineer: Pyburn & Odom, Inc.
Project Limits: Burbank Drive to Highland Road
Project Linear Footage: 2905
Detailed Description: This project will provide a link from Essen-Staring Lane directly to Burbank Drive by adding an extension to Staring Lane. The right of way for this project has already been acquired by DOTD. Project features include construction of sound walls along the Highland Creek Subdivision that border the roadway right of way and a bridge crossing Bayou Fountain. It includes the Bayou Fountain channel re-alignment that parallels the roadway to minimize proposed bridge length crossing Bayou Fountain. It will provide an improved north-south corridor when combined with the proposed Staring Lane improvement project.
Project Budget: Present Day Cost $14,438,974.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 60%
                         
Project Progress: Installation of the new 64" sewer force main has been completed. All drainage pipes have been installed. The contractor is continuing the asphalt widening of Highland Road to install a left turn lane in each direction.
Project Look Ahead: After the new sewer is installed, the contractor will begin building the new road between Burbank and Highland. Sound walls will be installed along the side of the new road through the Highland Creek subdivision. The construction of the sound wall foundations is scheduled to begin in September. Bridge construction will continue.

CONSTRUCTION INFORMATION
Contractor Name: James Construction Group, LLC
Construction Amount: $15,942,215.80
Construction Duration: 660 days
Construction Start Date: 2/2/2009
Construction End Date: 11/24/2010