PROJECT INFORMATION
Project ID: R1  Project Layout
Project Name: Pecue Re-alignment at Perkins
City Parish Project No: 07-CS-HC-0024
DOTD Project No: 258-01-0045
Design Engineer: Evans-Graves Engineers, Inc.
Project Limits: Perkins Road to Kansas City South Railroad
Project Linear Footage: 3500
Detailed Description: This project starts at the existing Pecue Lane (south leg) / Perkins Road intersection and ties back into existing Pecue Lane at the Kansas City Southern (KCS) railroad. Currently, the north and south legs of Pecue Lane are offset approximately 400 feet at their respective intersections with Perkins Road. This project also includes a new traffic signal at the new Realigned Pecue Lane / Perkins Road intersection. When combined with the existing Stumburg Lane project, the proposed project AA - Stumburg Lane Extension, and proposed project R2 - Pecue Lane and I-10 Interchange, a south-north connection will be provided that extends from Perkins Road to Coursey Boulevard. The project will provide an alternative to both Siegen Lane and Highland Road once the I-10 diamond interchange is constructed.
Project Budget: Present Day Cost $3,070,930.00
Project Files:
Project
Summary
Photo
Gallery

PROJECT SCHEDULE
Planning 100% Design 100% ROW 100% Construction 100%
       
Project Progress: Construction is complete.
Project Look Ahead: Roadway is now open to traffic.

CONSTRUCTION INFORMATION
Contractor Name: Boone Services, Inc.
Construction Amount: $2,438,162.00
Construction Duration: 291 Calendar Days
Construction Start Date: 8/26/2009
Construction End Date: 6/13/2010

Secure Login For questions and comments about this Green Light Plan project, please send email requests to Kimberlie Wessman at wessman@csrsonline.com or use our online feedback form.

This page was last updated on 9/1/2010 9:02:20 AM